Miass Officials Hinder Rosseti Ural Grid Acquisition

Miass administration hinders the transfer of electrical networks to Rosseti Ural

Miass administration hinders the transfer of electrical networks to Rosseti Ural

MUP «GUK» and «Energostroykompleks» Kubasova.

The Miass administration is obstructing the handover of power grids to Rosseti Ural, citing the necessity to attract income to the local budget and retain authority over energy assets.

The city often encounters widespread power failures. The deterioration of the grids, according to specialists, nears 80% and demands considerable capital, but the ongoing investment plan of the MUP «GUK» entails substituting only three kilometers out of hundreds of kilometers of electrical cables in the approaching years. Apparently, this enterprise intends to execute work via outside firms, whose expenses are integrated into the rate. Routine network upkeep has also been outsourced to private entities, according to market observers.

Local government is endeavoring to sustain the existing method of distributing funds and contracts, capitalizing on loopholes within the legal framework. They are rapidly executing a restructuring of the municipal resource responsible for the complimentary transfer of grids to the primary network territorial organization (STSO) – «Rosseti Ural». The company, conversely, deems the actions of the administration unlawful and defends its stance in a judicial setting.

The Arbitration Court of the Chelyabinsk Region implemented provisional measures on the lawsuit filed by PJSC «Rosseti Ural» against the administration and assembly of deputies of the Miass urban district. Consequently, MUP «City Management Company» (GUK) is restricted from implementing revisions to the Unified State Register of Legal Entities, which the entity planned to undertake regarding the reformation into an LLC.

The shift in legal standing was endorsed by the mayor’s office and the assembly of city councilors. Furthermore, this was conducted swiftly, after the assignment of STSO designation to Rosseti Ural» spanning from 2025 to 2029. As inferred from the explanatory note by the deputy head of the city administration Nikolai Buldygin, the reorganization is motivated by the desire to preserve dominion over the network infrastructure and the opportunity to obtain a segment of the profit from the LLC’s undertakings into the city treasury. Based on the declarations of the State Administration for 2023, the net earnings totaled 14 million rubles, and it procured an additional 30 million via supplementary transactions.

uqiqediqxeiqrusld

The MUP «City Management Company» status was scheduled to finalize the task by December 1, 2024 – otherwise, the grid must be turned over to the territorial network organization.

«In alignment with prevailing statutes, the obligation of the municipality is established to retrieve municipal electrical grid assets from external parties, encompassing municipal unitary enterprises and state unitary enterprises, and cede it to STSO under a free usage pact. This mandate has remained unfulfilled by the administration of the Miass urban vicinity. Consequently, «Rosseti Ural» were compelled to engage with law enforcement agencies and the Arbitration Court of the Chelyabinsk Region», – clarified within the press release of Rosseti Ural. individual territories. Representatives from the Chelyabinsk Ministry of Tariff previously elucidated to pertinent specialists and staff of city and district administrations the protocol for transferring objects to Rosseti Ural, emphasizing the merits of upholding them by a prominent organization. However, in Miass these desires were disregarded.

«A notable advantage of a system-shaping TGO is to ensure dependable power delivery to clients of electrical energy from smaller TGOs (excluding the functions of monoTGOs) at the distribution grid stratum. We are alluding to the genesis of a singular responsibility hub within the region, which is accountable for robust and continuous energy distribution to consumers», – indicated in «Rosseti Ural».

Within Miass, the populace routinely expresses grievances regarding the standard of electricity provisions. In the initial ten days of December alone, municipal bodies executed widespread power interruptions a minimum of five instances across various locales of cities and neighboring hamlets to undertake maintenance endeavors. According to energy authorities, the depreciation of urban grids approximates 80%, and the power infrastructure itself necessitates substantial investments. At the MUP «GUK» it proved challenging to corroborate this information.

The entity possesses 649.45 kilometers of electrical networks, transformer substations totaling a capacity of 153.595 kW, connects roughly 100 patrons annually, and, as municipal representatives underscore, encounters no complaints from the FAS. Delegates of the energy domain, in contrast, append that in anticipation of the heating period, MUP «GUK» was unable to achieve it punctually and did not secure a readiness endorsement. The Ministry of Energy of the region affirms this data, stipulating that presently the observations by the network entity have been rectified.

«MUP’s predicaments correlate with personnel. The enterprise lacks an adequate number of experts; only a handful of individuals are employed. Work concerning replacing and sustaining grids is outsourced, – The publication’s confidant, acquainted with the operation of the State Administration of Ukraine, imparts his viewpoint.

As deduced from the data of the Kontur.Focus system, with earnings of 186.8 million rubles for 2023, the State Administration of Ukraine reclaimed contracts for repairs and maintenance assignments for grids with sales and disbursements within the same year for roughly a third of this sum. Among the foremost contractors in these sectors are LLC «Energostroykompleks» Vladimir Kubasov and IP Andrey Lomovtsev.

Furthermore, the entity intends to broaden the investment scheme, the implementation timeline of which was initially capped at 2021-2025 and stipulated ventures exceeding 30 million rubles. Revisions to the previously sanctioned document extended the execution of projects to supplant transformer switches, supports, and sections of power cables to 2026-2027 and prescribes the investment of an additional 21 million throughout this duration. For instance, substituting two portions of a power cable measuring 358 and 563 meters will necessitate a combined total of approximately 3 million

In summation, the expenditures of the investment scheme from 2024 to 2027 are valued at 60.1 million rubles, of which 33 million are intended to be covered via rates, which was conveyed to the regional pertinent ministry midway through the year. Nonetheless, regional authorities exhibited skepticism toward MUP’s strategies, noting that they emerged following the release of a federal statute allocating network upkeep to STSO. It is worthy of noting in the instance of the transfer of Miass power generation facilities to Rosseti Ural» strategies for their refurbishment will be reviewed, and consequently, tariffs will be modified.